Sussex Turnpike Detour

Posted: August 10, 2011

Construction of the Sussex Turnpike sanitary sewer project by P.M. Construction of Hillside, NJ is slated to begin on or about August 15, 2011.

The project boundaries are from the intersection of Brookside Road and Sussex Turnpike to the intersection of Church Road and Sussex Turnpike.

The project is expected to last three months. During this time, expect traffic delays and road detours (see below) along these portions of Sussex Turnpike.

Please also note that no sewer connections will be permitted until additional upgrades to the Randolph Township sewer system are completed.

Questions? Please contact the Randolph Township Engineering Department at 973.989.7066.



Detours
Sussex Turnpike detour

Phase 1: Work area on Sussex Turnpike from Brookside Road to Millbrook Avenue

Westbound traffic on Sussex Turnpike will make a left onto Brookside Road. It will continue on Brookside Road until Old Brookside Road. It will make a right onto Old Brookside Road and follow it back to the intersection with Sussex Turnpike.

Eastbound traffic on Sussex Turnpike will make a right onto Old Brookside Road. It will continue to the end to the intersection with Woodland Road. It will make a left onto Woodland Road. It will continue on Woodland Road, which becomes Brookside Road, until it reaches the intersection with Sussex Turnpike at the end.

Southbound traffic on Millbrook Avenue will make a right at the intersection with Sussex Turnpike. It will continue on Sussex Turnpike until it gets to Old Brookside Road. It will make a left onto Old Brookside Road and follow the detour as above for eastbound traffic.

Phase 2: Work area on Sussex Turnpike from Millbrook Avenue to Church Road

Westbound traffic on Sussex Turnpike will make a right onto Millbrook Avenue. It will continue on Millbrook Avenue until the intersection with Church Road. It will make a left onto Church Road and follow that around until it ends at the intersection with Sussex Turnpike.

Eastbound traffic on Sussex Turnpike will make a left onto Church Road. It will follow it around until it ends at the intersection with Millbrook Avenue. It will make a right onto Millbrook Avenue and continue until it ends at the intersection with Sussex Turnpike.