Street NameDates of MillingDates of Paving
Springhill Road - Forrest Road to #407/97/11-12
Musiker Avenue - Morey Lane to #747/97/10
Musiker Avenue - Knights Bridge to Morey Lane7/97/10
Trowbridge Drive - Tammy Hill to Black Birch7/97/11-12
Indian Trail Road - Glen Road to Blue Fern Lane7/107/12-13
Everdale Road - Millbrook Avenue to Pierson’s Hill Road7/107/12-13
Blue Fern Lane - Entire length7/107/12-13
Mount Pleasant Tpke. - Appio Drive to township line7/117/13
Quaker Avenue - Fairfield Avenue to Center Grove Road7/117/13
Hilltop Drive - Dead end to Mostyn Road7/127/16
Clearview Drive - #14 to Mac Spar Drive7/127/16