2022 Road Resurfacing Program
Posted: June 6, 2022
Randolph Township evaluates the condition of the road system on an annual basis as part of its ongoing road maintenance program.
This evaluation program is a collaborative effort between the engineering and public works departments. The program takes into account the perspectives of both departments and synthesizes the input received into a comprehensive annual evaluation of the township road system.
This program tracks all of the 154 center line miles of township roadways.
The funding for this year is similar to last year, allowing for approximately the same amount of miles of roadway maintenance. Eighteen roads, or 5 miles, are scheduled for resurfacing. As in past years, if funds are available after the roads scheduled for resurfacing have been completed, additional roads could be added prior to the end of the year.
Milling of the following roads is tentatively scheduled to begin August 3, 2022, weather permitting. Residents living on these roads who were interested in tying into underground utilities should have done so by now.
Washington Valley Road | Entire length south of Sussex Turnpike |
Knights Bridge Drive | Entire length |
Rock Ledge Road | Entire length |
Cedar Terrace | Entire length |
Linda Terrace | Entire length |
Phyllis Place | Musiker Avenue/west to Blanchard Court |
Cambridge Court | Entire length |
Concord Road | Entire length |
Aldebaran Drive | Deneb Road to Olde York Road |
Longview Avenue | Center Grove Road to Melanie Lane |
Ridge Road | Concord Road to Dogwood Trail |
Mt Pleasant Turnpike | Route 10 to Appio Drive |
Old Chimney Road | Entire length |
Quail Run | Entire length |
Birchwood Road | Entire length |
Hemlock Road | Entire length |
Cypress Place | Entire length |
Elm Street | Entire length |
If you have questions, please call the engineering office at 973.989.7069.