Randolph Township evaluates the condition of the road system on an annual basis as part of its ongoing road maintenance program.

This evaluation program is a collaborative effort between the engineering and public works departments. The program takes into account the perspectives of both departments and synthesizes the input received into a comprehensive annual evaluation of the township road system.

This program tracks all of the 154 center line miles of township roadways.

The funding for this year is similar to last year, allowing for approximately the same amount of miles of roadway maintenance. Eighteen roads, or 5 miles, are scheduled for resurfacing. As in past years, if funds are available after the roads scheduled for resurfacing have been completed, additional roads could be added prior to the end of the year.

Milling of the following roads is tentatively scheduled to begin August 3, 2022, weather permitting. Residents living on these roads who were interested in tying into underground utilities should have done so by now.

Washington Valley RoadEntire length south of Sussex Turnpike
Knights Bridge DriveEntire length
Rock Ledge RoadEntire length
Cedar TerraceEntire length
Linda TerraceEntire length
Phyllis PlaceMusiker Avenue/west to Blanchard Court
Cambridge CourtEntire length
Concord RoadEntire length
Aldebaran DriveDeneb Road to Olde York Road
Longview AvenueCenter Grove Road to Melanie Lane
Ridge RoadConcord Road to Dogwood Trail
Mt Pleasant TurnpikeRoute 10 to Appio Drive
Old Chimney RoadEntire length
Quail RunEntire length
Birchwood RoadEntire length
Hemlock RoadEntire length
Cypress PlaceEntire length
Elm StreetEntire length

If you have questions, please call the engineering office at 973.989.7069.