The Township of Randolph has scheduled the following roads to be milled and/or resurfaced beginning August 2024, weather permitting:
| Road | Length | Tentative Milling Date | Tentative Paving Date |
|---|
| Old Shunpike Road | Brookside Road to Barbara Drive | August 13 | August 22 |
| Powder Horn Road | Entire Length | August 13 | August 22 |
| Morey Lane | Musiker Avenue to House #14 | August 13 | August 21 |
| Kings Brook Court | Entire Length | August 19 and 20 | August 27 and 28 |
| Drake Court | Entire Length | August 12
| August 20 and 21 |
| Bonnell Lane | Entire Length | August 12 | August 20 |
| Elaine Court | Entire Length | August 12 | August 21 |
| Sweetwood Drive | Entire Length | August 16 and 19 | August 26 and 27 |
| Lexington Court | Entire Length | August 20 | August 28 |
| Jodilee Lane | Entire Length | August 14 | August 23 |
| Brandywine Court | Entire Length | August 14 | August 23 |
| Old Brookside Road | House #74 to Mendham Town Line | August 14 | August 22 and 23 |
| Shongum Road | House #81 to Denville Town Line | August 15 | August 23 and 26 |
| Ironia Mendham Road | South Road to bridge (both lanes) Dover Chester Road to bridge (one lane) | August 19 | August 29 |
It is important to know that the township prohibits any excavation of newly repaved streets for a five-year time frame. Accordingly, if you are contemplating a tie-in to any underground utilities or sump pumps to the storm drain, you must act immediately. Additionally, if water is discharged from your property to the road, you must take corrective action and discharge this water to a township storm basin. If you need to open the road after it has been paved, you will be required to pay a surcharge plus the road opening fee. Should you have any questions, please contact the Engineering Department at (973) 989-7066.
The paving of these roads should take approximately two weeks to complete, weather permitting. As the summer progresses, please check out our website (www.randolphnj.org) and social media for more specific dates for the milling and paving of these streets.
Your garbage and/or recycling may be impacted by the paving of your street. Blue Diamond will make every effort to pick up so you must have your garbage and/or recycling out the night before your scheduled day and Blue Diamond will pick up on your street before 6:00am.
We thank you for your cooperation and patience during this project. Please accept our apologies in advance for any inconveniences that may be experienced. This tentative schedule is subject to change. We will do our best to complete the paving in a timely manner.